The Alliance Team developed Programming Documentation at Naval Station, Sigonella, Italy. Cost estimates were developed using Micro-Computer Aided Cost Estimating System (MCACES) MII software for 35%, 65%, and 100% Design Submittals. The latest version of the Cost Book along with local vendor quotes solicited from host nation contractors and suppliers, conducted host nation labor audit, and detailed quantity take-offs (QTO). Standard work breakdown structures provided with MII along with the Basis of Cost Estimate (BoCE) was developed to provide the project assumptions and local cost adjustments.
Communications Center, Naval Air Station Sigonella
Project facts
- Services
- Location
- NAS Sigonella, Italy
- Status
- Completed
- Size
- 6,607 m²